Building Program Background

Dedication For Our New Facilities

October 10, 2007

~~~See Details~~~

Building Complete -

Moved In and Functional -

Mid July 2007

Newsletter June 10

Progress Of Work In Last Month

  • Installation of ceiling tile, millwork and trim and plumbing fixtures has been completed!

  • Lighting system for the Parish Hall has been installed!

  • Installation of kitchen equipment is complete!

  • The floor tile, wood and carpet finishes are nearly complete.

  • Installation of wood doors has begun.

Bells Are Installed

July 31,2007


See More Bell Pictures HERE

Our New Building - Almost Done!

July 31,2007


See More July Pictures HERE


Our New Building - Going Up!

May 2,2007


See More May Pictures HERE


Our New Building - Going Up!

March 9,2007


See More March Pictures HERE


Our New Building - Going Up!

January 19,2007


See More January Pictures HERE


New Parish Hall - Click for More Pictures

December 8,  2006


See More December Pictures HERE


See - Elf Work On the Construction Site


Click to See Pictures of Our New Building Going Up

Nov 4, 2006


See More November Pictures HERE

Newsletter May 13

Progress Of Work In Last Month

  • Landings, ramps & planters are 100% complete!

  • Ductwork is 100% complete!

  • Wall plumbing and electrical rough-in is 100% complete!

  • Brick veneer is 100% complete!

  • Exterior trim is 100% complete!

  • Glass and glazing is 95% complete

  • Playground deck is 95% complete

  • Painting exterior is 80% complete

  • Painting interior is 20% complete

  • Bell Tower is 75% complete

  • Sidewalk work begun

Planned Progress for the next month:

  • Continue work on sidewalks

  • Start paving

  • Continue painting

  • Finish ceiling grid

  • Start ceiling tile

  • Finish lighting

  • Start floor finishes

  • Continue Bell Tower

  • Start kitchen equipment

  • Start youth area work

Newsletter April 15

Progress Of Work In Last Month

  • Wall plumbing rough-in is complete!

  • Wall electrical rough-in is complete!

  • Overhead sprinkler piping is complete!

  • Sub-ceiling work is complete!

  • Exterior trim is almost complete!

  • Ductwork is almost complete!

  • Brick veneer work is almost complete!

  • Painting has begun
     

Planned Progress for the next month:

  • Continue work on landings, ramps and planters

  • Finish ductwork

  • Continue painting

  • Continue work on bell tower

  • Continue gypsum board walls

  • Start ceiling grid

  • Start lighting

Newsletter March 11

Progress Of Work In Last Month

  • Window installation is complete!

  • Site utilities are complete!

  • Heating water piping complete!

  • Wall plumbing rough-in is almost complete!

  • Wall electrical rough-in almost complete!

  • Ductwork is almost complete!

  • Exterior trim is almost complete!

  • Brick veneer work is continuing

Planned Progress for the next month:

  • Continue work on landings, ramps and planters

  • Finish ductwork

  • Finish overhead sprinkler piping

  • Continue work on bell tower

  • Continue brick veneer

  • Continue gypsum board walls

Newsletter February 11

Progress Of Work In Last Month

  • Wood wall framing is complete!

  • HVAC is complete!

  • Roof decking is complete!

  • Hollow metal frames are complete!

  • Exterior trim work is continuing

  • Ductwork is almost complete

  • Wall plumbing and electrical rough-in is almost complete

  • Brick veneer work has begun

  • Bell tower work has begun

  • Site utilities work has begun

Planned Progress for the next month:

  • Continue work on landings, ramps and planters

  • Finish ductwork

  • Continue brick veneer

  • Finish installing windows

  • Finish overhead sprinkler piping

  • Continue sprinkler rough-in

  • Continue roof shingles

  • Finish site utilities

  • Continue work on bell tower

 

Newsletter January 26,2007

Progress Report From The Building Committee

  • Wall sheathing is complete!

  • Roof trusses are complete!

  • CMU masonry is complete!

  • CMU damp-proofing is complete!

  • Wood wall framing is almost complete

  • Roof decking and felt is 85% complete

  • HVAC is 70% complete

Planned Progress for the next month:

  • Work on landings, ramps, planters

  • Continue hollow metal door frame work

  • Finish wood decking

  • Continue brick veneer

Newsletter - October 8, 2006

PROGRESS OF WORK SINCE THE LAST UPDATE. . . We are ON Schedule !

 Layout is 100% complete
 Concrete building foundations are being finished
 Site storm drains are complete
 Underground plumbing is being roughed-in
 Underground electrical is being roughed-in
 ½ of the building floor slab has been poured (as of this writing)
 Steel erection has begun
 

Newsletter - September 10, 2006..

    UPDATE FROM THE BUILDING COMMITTEE:

  • Exterior perimeter foundation footings are nearing completion.

  • Underground storm drainage is completed. Mechanical subcontractor is presently working on underground plumbing lines at both the chapel and in new construction areas.

  • In the weeks ahead JESCO will begin to form and pour concrete foundation walls.

  • Concrete floor slab construction work can begin when foundation walls and under-slab plumbing is complete

Newsletter - August 2, 2006...

During the next few weeks, earthwork, and excavation will continue. Storm drainage will be completed and concrete foundations will be poured. In addition, plumbing and electrical work will start being roughed-in. Things are going well and we are on schedule!

--Betty Lee Marshall, Building Committee Chair
 

Newsletter - July 17, 2006...

JESCO is presently completing site preparation and dirt work. Depending on the weather, all compacted site fill will be in place with in a matter of days. In the coming weeks reinforcing steel will be arriving on site, and building foundation work will begin. Excavation for and placement of building and site drainage systems will run concurrently with foundation work.

Breaking Ground

June 30th, 2006

 


A Prayer for All Saints' Capital Campaign

Almighty God, whose loving hand has given us all that we possess: Bless the parish of All Saints at this time in our history. Grant us guidance, perseverance, and obedience as we seek The Way Ahead. Give us a spirit of gratefulness as we discern our personal responsibilities toward one another and to this campaign; and give us the wisdom to understand that we are each part of the greater community of faith which is your Holy Church. Grant this, we pray, so that we may continue and grow in the ministry that you have given to us, to be witnesses of your love to our neighbors, our community, and the world. We ask this, emboldened by the Holy Spirit, in the name of your Son, our Savior, Jesus Christ. Amen.