Dedication For Our New
Facilities
October 10, 2007
~~~See
Details~~~

Building Complete -
Moved In and Functional -
Mid July 2007

Newsletter June 10
Progress Of Work
In Last Month
-
Installation of
ceiling tile, millwork and trim and plumbing fixtures has been
completed!
-
Lighting system for
the Parish Hall has been installed!
-
Installation of
kitchen equipment is complete!
-
The floor tile, wood
and carpet finishes are nearly complete.
-
Installation of wood
doors has begun.

Newsletter May 13
Progress Of Work
In Last Month
-
Landings, ramps &
planters are 100% complete!
-
Ductwork is 100%
complete!
-
Wall plumbing and
electrical rough-in is 100% complete!
-
Brick veneer is 100%
complete!
-
Exterior trim is 100%
complete!
-
Glass and glazing is
95% complete
-
Playground deck is
95% complete
-
Painting exterior is
80% complete
-
Painting interior is
20% complete
-
Bell Tower is 75%
complete
-
Sidewalk work begun
Planned Progress for
the next month:

Newsletter April 15
Progress Of Work
In Last Month
-
Wall plumbing
rough-in is complete!
-
Wall electrical
rough-in is complete!
-
Overhead sprinkler
piping is complete!
-
Sub-ceiling work is
complete!
-
Exterior trim is
almost complete!
-
Ductwork is almost
complete!
-
Brick veneer work is
almost complete!
-
Painting has begun
Planned Progress for
the next month:
-
Continue
work on landings, ramps and planters
-
Finish
ductwork
-
Continue
painting
-
Continue
work on bell tower
-
Continue
gypsum board walls
-
Start
ceiling grid
-
Start
lighting

Newsletter March 11
Progress Of Work
In Last Month
-
Window installation
is complete!
-
Site utilities are
complete!
-
Heating water piping
complete!
-
Wall plumbing
rough-in is almost complete!
-
Wall electrical
rough-in almost complete!
-
Ductwork is almost
complete!
-
Exterior trim is
almost complete!
-
Brick veneer work is
continuing
Planned Progress for
the next month:
-
Continue
work on landings, ramps and planters
-
Finish
ductwork
-
Finish
overhead sprinkler piping
-
Continue
work on bell tower
-
Continue
brick veneer
-
Continue
gypsum board walls

Newsletter February 11
Progress Of Work
In Last Month
-
Wood wall framing is
complete!
-
HVAC is complete!
-
Roof decking is
complete!
-
Hollow metal frames
are complete!
-
Exterior trim work is
continuing
-
Ductwork is almost
complete
-
Wall plumbing and
electrical rough-in is almost complete
-
Brick veneer work has
begun
-
Bell tower work has
begun
-
Site utilities work
has begun
Planned Progress for
the next month:
-
Continue
work on landings, ramps and planters
-
Finish
ductwork
-
Continue
brick veneer
-
Finish
installing windows
-
Finish
overhead sprinkler piping
-
Continue
sprinkler rough-in
-
Continue
roof shingles
-
Finish
site utilities
-
Continue
work on bell tower

Newsletter January
26,2007
Progress Report From The Building
Committee
-
Wall
sheathing is complete!
-
Roof
trusses are complete!
-
CMU
masonry is complete!
-
CMU
damp-proofing is complete!
-
Wood
wall framing is almost complete
-
Roof
decking and felt is 85% complete
-
HVAC is
70% complete
Planned Progress for
the next month:
-
Work on
landings, ramps, planters
-
Continue
hollow metal door frame work
-
Finish
wood decking
-
Continue
brick veneer

Newsletter - October 8,
2006
PROGRESS
OF WORK SINCE THE LAST UPDATE. . .
We are ON Schedule
!
Layout is 100% complete
Concrete building foundations are being finished
Site storm drains are complete
Underground plumbing is being roughed-in
Underground electrical is being roughed-in
½ of the building floor slab has been poured (as of this writing)
Steel erection has begun

Newsletter - September 10,
2006..
UPDATE FROM THE
BUILDING COMMITTEE:
Exterior perimeter foundation footings are nearing completion.
Underground storm drainage is completed. Mechanical subcontractor is
presently working on underground plumbing lines at both the chapel and
in new construction areas.
In the weeks ahead JESCO will begin to form and pour concrete
foundation walls.
Concrete floor slab construction work can begin when foundation walls
and under-slab plumbing is complete

Newsletter - August 2,
2006...
During the next few
weeks, earthwork, and excavation will continue. Storm drainage will be
completed and concrete foundations will be poured. In addition, plumbing
and electrical work will start being roughed-in. Things are going well and
we are on schedule!
--Betty Lee Marshall, Building Committee Chair

Newsletter - July 17,
2006...
JESCO is presently
completing site preparation and dirt work. Depending on the weather, all
compacted site fill will be in place with in a matter of days. In the
coming weeks reinforcing steel will be arriving on site, and building
foundation work will begin. Excavation for and placement of building and
site drainage systems will run concurrently with foundation work.

 |
|
Breaking Ground
June 30th, 2006 |

|
A Prayer
for All Saints' Capital Campaign |
|
Almighty God, whose
loving hand has given us all that we possess: Bless the parish of All
Saints at this time in our history. Grant us guidance, perseverance,
and obedience as we seek The Way Ahead. Give us a spirit of
gratefulness as we discern our personal responsibilities toward one
another and to this campaign; and give us the wisdom to understand
that we are each part of the greater community of faith which is
your Holy Church. Grant this, we pray, so that we may continue and
grow in the ministry that you have given to us, to be witnesses of
your love to our neighbors, our community, and the world. We ask
this, emboldened by the Holy Spirit, in the name of your Son, our
Savior, Jesus Christ. Amen. |
|